Project Update – March 2025
The Lower Ground Floor slab is complete, and the Ground Floor is in progress, with completion expected by next week.

Project Update – March 2025
Slabs complete up to P1 and P1 mezzanine slab is in progress. Lower Ground Floor formwork to start next week.

Project Update – Feb 2025
Slab on grade work is complete. Formwork continues to progress on P1 suspended slab.