Project Update – Dec 2024

Project Update – Dec 2024

The raft slab is currently in progress. Columns and foundation walls following the progression of raft slab.

Project Update – Nov 2024

Project Update – Nov 2024

Concrete and waterproofing progressing in preparation for raft slab, followed by the commencement of foundation walls.

Project Update – Oct 2024

Project Update – Oct 2024

Vertical drilling has been completed in its entirety. Bulk excavation is currently underway, while tieback and lagging operations are continuing to bottom elevation.