Project Updates

Project Update – June 2025

Project Update – June 2025

Level 4 slab has been completed, and parapet work is currently progressing. Construction of Level 5 walls and columns is underway, with completion expected by mid-July. Reshoring removal is in progress, and preparations for window installation to commence shortly.

Project Update – June 2025

Project Update – June 2025

Construction work on the Level 4 slab and parapets is ongoing, with completion anticipated by the end of June. Meanwhile, mechanical and electrical installations continue to progress steadily within the parking garage.

Project Update – May 2025

Project Update – May 2025

The Level 3 slab has been completed, and construction of Level 4 is currently in progress, with completion expected by mid-June. Mechanical and electrical works have commenced in the parking garage.

Project Update – May 2025

Project Update – May 2025

The Level 2 slab has been completed, and construction of Level 3 is currently in progress, with completion expected for next week. Construction of Level 4 to begin immediately after.

Project Update – April 2025

Project Update – April 2025

The mezzanine level and the south elevation of Level 2 have been completed, while construction of the remaining sections of Level 2 is ongoing and expected to be completed by the end of May.

Project Update – April 2025

Project Update – April 2025

The ground floor slab has been completed, and construction of the columns and walls for the mezzanine level is currently in progress.

Project Update – March 2025

Project Update – March 2025

The Lower Ground Floor slab is complete, and the Ground Floor is in progress, with completion expected by next week.

Project Update – March 2025

Project Update – March 2025

Slabs complete up to P1 and P1 mezzanine slab is in progress. Lower Ground Floor formwork to start next week.

Project Update – Feb 2025

Project Update – Feb 2025

Underground drainage system works, and slab-on-grade continue to progress on the South side. Completion of slab-on-grade and P1 suspended slab on the North side. Columns and walls to commence mid-February on the North side.  

Kipling Station Condos

5251 Dundas St W, Etobicoke, ON M9B 1B1