Project Updates

Project Update – Dec 2024

Project Update – Dec 2024

The raft slab is currently in progress. Columns and foundation walls following the progression of raft slab.

Project Update – Nov 2024

Project Update – Nov 2024

Concrete and waterproofing progressing in preparation for raft slab, followed by the commencement of foundation walls.

Project Update – Oct 2024

Project Update – Oct 2024

Vertical drilling has been completed in its entirety. Bulk excavation is currently underway, while tieback and lagging operations are continuing to bottom elevation.

Project Update – Sept 2024

Project Update – Sept 2024

Following the successful demolition, site preparation is now underway for shoring and excavation. Crews are actively working to mobilize equipment and materials. Residents and pedestrians may expect increased truck traffic along Dundas St W.

Project Update  – Aug 2024

Project Update – Aug 2024

The demolition of the single-storey Starbucks building at 5251 Dundas St W has wrapped up and the site is now clear and ready for the next phase of construction.

Kipling Station Condos

5251 Dundas St W, Etobicoke, ON M9B 1B1