Project Updates
Project Update – Dec 2024
The raft slab is currently in progress. Columns and foundation walls following the progression of raft slab.
Project Update – Nov 2024
Concrete and waterproofing progressing in preparation for raft slab, followed by the commencement of foundation walls.
Project Update – Oct 2024
Vertical drilling has been completed in its entirety. Bulk excavation is currently underway, while tieback and lagging operations are continuing to bottom elevation.
Project Update – Sept 2024
Following the successful demolition, site preparation is now underway for shoring and excavation. Crews are actively working to mobilize equipment and materials. Residents and pedestrians may expect increased truck traffic along Dundas St W.
Project Update – Aug 2024
The demolition of the single-storey Starbucks building at 5251 Dundas St W has wrapped up and the site is now clear and ready for the next phase of construction.